NARAYANGADH: Vehicular movement along the Narayangadh-Mugling road section will be suspended for five hours daily to facilitate landslide prevention work in the Tuinkhola area.
The District Administration Office, Chitwan, has decided to close the road from 11 am to 4 pm every day starting December 29 until further notice.
Assistant Chief District Officer Ishwori Prasad Sharma said the movement of all types of vehicles would be halted during the designated hours, considering the potential risks associated with the ongoing landslide prevention work.
As landslides continue to affect the Tuinkhola area, the Road Division Office, Bharatpur, has initiated efforts to find a long-term solution by adopting specialised engineering technologies. Various measures have been introduced since last year to prevent landslides and road blockages during both the monsoon and winter seasons.
The planned work includes the use of the ‘nailing’ technique, which involves removing large rocks and inserting steel rods into the slope to stabilise the landslide-prone area. Horizontal drainage systems and bioengineering measures will also be implemented to manage water flowing from the hillside.
Amit Kumar Sharma, chief engineer at the Road Division Office, Bharatpur, said bioengineering techniques would be applied in two-dimensional and three-dimensional forms, depending on the nature of the slope, while nailing technology would be used primarily to strengthen the unstable terrain.
Landslide prevention work in Tuinkhola, which had remained suspended since last Ashoj, is now being resumed. Sharma said the work had previously continued even during the closure of the Prithvi Highway at Krishna Bhir. However, construction in Tuinkhola was temporarily halted to facilitate the reopening of the Krishna Bhir section.
According to Sharma, the condition of the road suggests that the work may require at least 15 days of closure. He added that the exact duration of the restrictions would be determined following a technical assessment, and the road would remain closed during the specified hours until further notice.
Sharma also said that landslide prevention work at Ghoptebhir, near Mugling along the Prithvi Highway, is expected to be completed by tomorrow, allowing the highway to reopen the following day. Work in Tuinkhola will resume after the Ghoptebhir project is completed.
The administration has clarified that the Prithvi Highway connecting Kathmandu and Pokhara via Mugling and Aanbukhaireni will remain operational.
Apologising for the inconvenience caused by the road closure, the administration has urged passengers and motorists to plan their journeys accordingly.